Reliability-based maintenance scheduling of generating units in restructured power systems

Maintenance scheduling of generating units in restructured power systems is a collaborative and interactive process between independent system operators (ISOs) and generating companies (GENCOs). The ISO should comply with GENCO maintenance preferences subject to targeted system reliability levels. This process might be multistage since the admission of all initial unit outage requests may threaten system reliability. Hence, the ISO accepts some proposals and determines alternatives for the remaining units. The GENCOs are then allowed to confirm the alternatives or revise them. In this paper the ISO problem of generating unit maintenance scheduling is tackled. The objective function is to minimize the deviation of awarded schedule from the requested schedule, as measured in MW weeks. A novel and effective optimization technique is developed to solve the problem at hand. In the proposed methodology, risk leveling and dynamic programming optimization algorithms are concurrently utilized to lessen the computation burden and enhance the solution process. The effectiveness of the proposed method and its applicability to real-life systems are verified by examining the generation section of the IEEE reliability test system (IEEE-RTS). The performance of the new method is also compared with that of the individual risk leveling approach.

Reliability-based maintenance scheduling of generating units in restructured power systems

Maintenance scheduling of generating units in restructured power systems is a collaborative and interactive process between independent system operators (ISOs) and generating companies (GENCOs). The ISO should comply with GENCO maintenance preferences subject to targeted system reliability levels. This process might be multistage since the admission of all initial unit outage requests may threaten system reliability. Hence, the ISO accepts some proposals and determines alternatives for the remaining units. The GENCOs are then allowed to confirm the alternatives or revise them. In this paper the ISO problem of generating unit maintenance scheduling is tackled. The objective function is to minimize the deviation of awarded schedule from the requested schedule, as measured in MW weeks. A novel and effective optimization technique is developed to solve the problem at hand. In the proposed methodology, risk leveling and dynamic programming optimization algorithms are concurrently utilized to lessen the computation burden and enhance the solution process. The effectiveness of the proposed method and its applicability to real-life systems are verified by examining the generation section of the IEEE reliability test system (IEEE-RTS). The performance of the new method is also compared with that of the individual risk leveling approach.

___

  • R0 Rk Rmax tk ∆R (tk) vector representing the effect on weekly LOLP of maintenance outage associated with unit k from weeks tkto tk+ dk N. Mohammadi Tabari, “A new approach for maintenance scheduling in restructured power systems”, PhD Disser- tation, Science and Research Branch of Azad University, Tehran, Iran, 2003.
  • M. Shahidehpour, M. Marwali, Maintenance Scheduling in Restructured Power Systems, Massachusetts, USA, Kluwer Academic Publishers, 2000.
  • H. Khatib, “Maintenance scheduling of generating facilities”, IEEE Transactions on Power Apparatus and Systems, Vol. 98, pp. 1604–1608, 1979.
  • R. Billinton, A. Abdulwhab, “Short-term generating unit maintenance scheduling in a deregulated power system using a probabilistic approach”, IEE Proceeding on Generation, Transmission, and Distribution, Vol. 150, pp. 463–468, 2003.
  • Y. Wang, E. Handschin, “Unit maintenance scheduling in open systems using genetic algorithm”, IEEE Transmission Distribution Conference, Vol. 1, pp. 334–339, 1999.
  • R. Billinton, S. Kumar, N. Chowdhury, K. Chu, K. Debnath, L. Goel, E. Khan, P. Kos, G. Nourbakhsh, J. Oteng- Adjei, “A reliability test system for educational purposes-basic data”, IEEE Transactions on Power Systems, Vol. 4, pp. 1238–1244, 1989. http://www.mathworks.com/products/matlab/, last access date: 12-17-2012, Matlab.
  • G. Lu, F. Wen, C.Y. Chung, K.P. Wong, “Generation unit maintenance scheduling in electricity market environ- ment”, Third International Conference on Electric Utility Deregulation and Restructuring and Power Technologies, pp. 720–725, 2008.
  • A.J. Conejo, R. Garcia-Bertrand, M. Diaz-Salazar, “Generation maintenance scheduling in restructured power systems”, IEEE Transactions on Power Systems, Vol. 20, No. 2, pp. 984– 992, 2005.
  • R. Eshraghnia, M.H.M. Shanechi, H.R. Mashhadi, “Generation maintenance scheduling in power market based on genetic algorithm”, Power Systems Conference and Exposition, pp. 1814–1819, 2006.
  • N. Kumarappan, P. Suriya, “Hybrid GA/SA based generation maintenance scheduling with line flow constraints in power market”, Joint International Conference on Power Electronics, Drives, and Energy Systems, pp. 1–8, 2010.