Trepça mine in Stantërg has used the highest
productivity and mining technique since 90s. Today this technique is practiced
almost in all working place. The purpose of this study is to determine the
productivity of the drilling machine with high productivity. The machinery has
worked in the working place so called P-140, in the X- horizon of “Trepca"
mine in Stantërg and the main goal is to set the parameters of the work and its
maximum activity - the rate of work according to their own specifications as: Work
force, Structure of the rock mass and; other difficulties arising from the
workplace. The goal is to do a study to increase efficiency and eliminate gaps
by workers and the leading body of the mine while working with the drilling
machine in order to increase the effect on drilling-mining (realize the largest
production and to enable and achieve higher productivity).
___
Designin of new underground mining facilities with dual function in the Pb-Zn mine of mazhiq Dr. Izet Zeqiri, Jahir Gashi, Rafet Zeqiri, University of Pristina, Kosovo
Gertsch R, Bullock R, (1998) Techniques in Underground Mining Society for Mining, Metallurgy, and Exploration Littleton, Co, USA
Spathis A., Gupta R. (2012) Tunnelling in Rock by Drilling and Blasting. Workshop hosted by frag blast The symposium on rock fragmentation by blasting, New Delhi, India,
Torbica S, Petrovic N, (1997) Metode i Tehnologija Podzemne Eksploatacije Neslojevitih Lezista Beograd