Application of Millisecond Delays for Improvement of Contour Blastings Results – Case Study Bellanica

The stability of the slopes is of the utmost importance during the exploitation works in surface mines and during the opening of roads, because this directly affects the results of the works and safety. Achieving the highest possible stability of the slopes is done using contour blastings, to make the cutting of the massive that is mined. But in order to achieve the best results in cutting the massive that is being mined, milliseconds delays should be used, in order to create free face before each subsequent blasthole, in this case the impact of drillings of the preliminary rows on behind them will reduced. With the application of milliseconds delays 17 [ms] between drillings in the row and 67 [ms] between rows, the impact of blastholes of the front rows will be very small or no impact at all on behind them, making it possible to form benches and slopes safe and without cracks. This enables us to have safe mining work and safe driving on the road.

___

  • Dzodič R, (1985) Tehnologija bušenja i miniranja, Prishtinë. (Drilling and mining technology) Pristina
  • Brahimaj I, (2008) Determining technical-economic parameters towards the advancement of massive detonations in exploring bauxites in Kosovo. M.Sc. thesis. Mitrovica.
  • Brahimaj I, (2012) Contribution in the selection of optimal parameters of massive detonations in the limestone deposits of Gremnik. Ph.D. thesis. Mitrovica
  • Brahimaj I., Brahimaj F, (2019). The massive and special blastings. Mitrovicë: University of Mitrovica "Isa Boletini".
  • Brahimaj F, (2013) Appliance of contour blasting within road infrastructure Morine – Merdare. Msc. thesis. Mitrovica.
  • Brahimaj F, (2014) Elaborate for blasting, Prishtina, Kosovo.
  • Brahimaj F, (2020) Contribution for improvement of contour blastings in forming final slopes on the roadways and surface mines. Ph.D. thesis. Stip
  • Brahimaj F., Dambov R., Brahimaj S, (2019). The contour blasting aplication in the Kosovo motorway project in Bellanica. XV International Conference of the Open and Underwater Mining of Minerals, (pp. 46-53). Varna.
  • Brahimaj F., Dambov R., Brahimaj A. (2019). The optimal parameters determination of drilling in the Kosovo motorway project in Bellanica. XV International Conference of the Open and Underwater Mining of Minerals, (pp. 39-45). Varna.
  • Brahimaj Sh, (2013) Opening and preparation of trenches on the highway Morine – Merdare. Msc. thesis. Mitrovica.
  • Dambov R, (2011). Method's of blasting. Stip: University "Goce Delcev.
  • Dambov R, (2013). Drilling and blasting. Stip: University "Goce Delcev".
  • Dambov R, (2015). Special Blastings. Stip: University "Goce Delcev", Faculty of Natural and Technical Sciences.
  • Kennedy B.A, (1990) Surface Mining, USA.
  • Milenko S, (2000). Blastings in surface exploitations. Bor: Institut of Bakar.
  • Nako I, (2001). Nonel initiation system. Tirane: Polytechnic University of Tirana.